Roofing & cladding
How many roof sheets do I need?
For a 10 m gable roof with a 4 m run at 22.5 degrees, Custom Orb at 762 mm cover comes to 30 sheets, each 4.82 m long, plus 506 roofing screws and 5 ridge capping lengths at 2400 mm.
Shopping list
| Item | Buy | Note |
|---|---|---|
| Custom Orb (corrugated) sheets, 4.82 m long | 30 sheets | 762 mm cover; order the length your supplier can cut (sheets can be supplied long) |
| Roofing screws | 506 screws | 5 per m² at 900 mm supports (Lysaght Table 3.8) |
| Ridge capping, 2400 mm lengths | 5 lengths | laps and hip ends not counted |
- Flashings, gutters, end laps and fixing detail depend on your roof and wind region: follow the Lysaght manual.
How this was worked out
- Pitch factor:
1 ÷ cos(pitch)
1 ÷ cos(22.5°) = 1.08 × - Sheet length (slope):
(run + overhang) × pitch factor
(4 + 0.45) × 1.082 = 4.82 m - Sheets per plane:
length ÷ cover width, rounded up
10000 ÷ 762 = 14 sheets - Sheets:
planes × sheets per plane × (1 + waste), rounded up
2 × 14 × 1.05 = 29.4 sheets - Roof area:
planes × length × slope length
2 × 10 × 4.82 = 96.33 m² - Screws:
area × screws per m² × (1 + waste)
96.3 × 5 × 1.05 = 506 screws
How the calculator gets to 30 sheets
The roof in this guide is 10 m long, with each plane running 4 m from the ridge down to the wall line at a pitch of 22.5 degrees. Custom Orb covers 762 mm per sheet, which is the cover width Lysaght gives for the corrugated profile. The calculator starts with a 0.45 m overhang and a 5% waste allowance for cut sheets, and the waste allowance is editable.
The order of work is fixed: pitch factor first, then sheet length along the slope, then sheets across each plane, then both planes with the waste allowance, then the round-up to whole sheets. Roof area and the screw count are built from those same numbers, so the shopping list and the area always describe the same roof.
Reading the working line by line
Each line of the working uses the one before it:
- Pitch factor 1.08, from 1 ÷ cos(22.5°). It converts a horizontal run into a distance along the slope.
- Sheet length 4.82 m, from (run + overhang) × pitch factor, which is (4 + 0.45) × 1.082. This is the length you order, measured along the slope rather than across the ceiling.
- Sheets per plane 14, from length ÷ cover width, rounded up: 10000 ÷ 762 gives 13.12, so 14 sheets run across the 10 m length.
- Sheets 29.4, from planes × sheets per plane × (1 + waste): 2 × 14 × 1.05. The 1.05 already contains the 5% allowance, so nothing is added again here. Rounded up, that is 30 sheets.
- Roof area 96.33 m², from planes × length × slope length: 2 × 10 × 4.82.
- Screws 506, from area × screws per m² × (1 + waste): 96.3 × 5 × 1.05. Lysaght's Installation Manual Table 3.8 gives 5 screws per square metre for Custom Orb at 900 mm support spacing.
Three roofs side by side
The same calculation, run on three roofs. Every figure below comes from the calculator.
| Roof length | Run per plane | Pitch | Profile | Sheet length | Sheets | Roof area | Screws | Ridge capping |
|---|---|---|---|---|---|---|---|---|
| 10 m | 4 m | 22.5° | Custom Orb | 4.82 m | 30 | 96 m² | 506 | 5 × 2400 mm |
| 7.62 m | 3 m | 15° | Custom Orb | 3.57 m | 21 | 54 m² | 286 | 4 × 2400 mm |
| 12 m | 5 m | 25° | Trimdek | 6.01 m | 34 | 144 m² | 910 | 5 × 2400 mm |
Trimdek also covers 762 mm, so the sheet count per plane moves only with roof length. Its higher screw count comes from both its larger area and its screw density: 144.3 m² × 6 screws per square metre × 1.05 = 910. Table 3.8 gives 6 screws per square metre for Trimdek at 900 mm support spacing. Flashings, gutters, end laps and fixing detail depend on your roof and wind region: follow the Lysaght manual.
Worked example
Take the 10 m gable roof, 4 m run, 22.5 degrees, Custom Orb.
- Pitch factor: 1 ÷ cos(22.5°) = 1.08.
- Sheet length along the slope: (4 + 0.45) × 1.082 = 4.82 m. That is the length to order for every sheet on both planes.
- Sheets per plane: 10000 ÷ 762 = 13.12, rounded up to 14.
- Both planes with waste: 2 × 14 × 1.05 = 29.4 sheets. The 1.05 is the waste multiplier, so the 5% is inside this figure.
- Round up: 29.4 becomes 30 sheets, all at 4.82 m.
- Roof area: 2 × 10 × 4.82 = 96.33 m². Screws: 96.3 × 5 × 1.05 = 506.
- Ridge capping: 10 m of ridge against 2400 mm lengths gives 5 lengths, since four lengths cover only 9.6 m.
What changes the answer
Pitch drives the pitch factor, and the pitch factor drives sheet length. It is 1.04 at 15 degrees, 1.08 at 22.5 degrees and 1.1 at 25 degrees, so sheet length is (run + overhang) × pitch factor: (3 + 0.45) × 1.035 = 3.57 m and (5 + 0.45) × 1.103 = 6.01 m. Longer roofs need more sheets across each plane, not longer ones.
Cover width matters as much. Klip-Lok 406 covers 406 mm and Klip-Lok 700 covers 700 mm, both narrower than the 762 mm cover of Custom Orb and Trimdek, so a narrower profile needs more sheets across the same roof length. The waste allowance is editable rather than fixed at 5%, and screw density follows the support spacing: Table 3.8 gives 4 screws per square metre for Custom Orb at 1200 mm and 5 at 900 mm.
Pitch also has to clear the profile's minimum. Lysaght's Flashing Guide gives a minimum pitch of 5 degrees for Custom Orb and 2 degrees for Trimdek.
Common mistakes
One error to avoid is adding the waste allowance twice. The working already reads 2 × 14 × 1.05 = 29.4. Adding another 5% would push it to about 31 sheets, one more than the job needs.
The second is rounding sheets per plane down instead of up. 10000 ÷ 762 is 13.12, and 13 sheets cover 9906 mm of a 10 m length, leaving the last 94 mm uncovered.
The third is ordering the run as the sheet length. The order length is 4.82 m, not 4 m and not 4.45 m, because the pitch factor converts the plan distance into distance along the slope.
Watch the ridge capping count too. Four 2400 mm lengths total 9.6 m, which falls short of a 10 m ridge; the calculator returns 5.
Frequently asked questions
Do I order 30 sheets or 29.4?
The calculation gives 29.4 sheets. You order whole sheets, so 30 at 4.82 m.
What length should the sheets be?
4.82 m on the 10 m roof. That figure is (4 + 0.45) × 1.082, the run plus overhang converted to slope length.
How many screws does a 96 m² roof need?
506 screws. The count is 96.3 m² × 5 screws per square metre × 1.05 for waste.
How many ridge capping lengths cover a 10 m ridge?
Five lengths at 2400 mm. Four lengths cover 9.6 m, which is short of 10 m.
Does a steeper pitch mean more sheets?
No, not the number of sheets across. The pitch factor rises with pitch, from 1.04 at 15 degrees to 1.1 at 25 degrees, so the sheet length and the roof area both grow while the number of sheets across stays the same.
Sources and assumptions
These are the settings behind every number above. Verified figures link to a source. Editable defaults are common rules of thumb: change them to match your product and your site.