Concrete & masonry
How much concrete for a shed base?
To determine how much concrete you need for a shed slab, you must calculate the volume based on the area and thickness of the slab, which for a 3 x 2.4 m shed at 100 mm thickness results in 84 bags of 20 kg mix or 0.8 m³ of ready-mix.
Shopping list
| Item | Buy | Note |
|---|---|---|
| Concrete mix, 20 kg bags | 84 bags | 0.00909 m³ per 20 kg bag (110 × 20 kg bags per m³, scaled by weight) |
| Crushed rock base (50 mm compacted, if used) | 0.86 t | 0.36 m³ compacted |
- Bag yields differ between brands (Boral lists 108 bags of 20 kg per m³, Cement Australia 110). Check the yield on your own bag.
How this was worked out
- Area:
length × width
3 × 2.4 = 7.2 m² - Volume:
area × thickness ÷ 1000
7.20 × 100 ÷ 1000 = 0.72 m³ - With waste:
volume × (1 + waste)
0.720 × 1.05 = 0.76 m³ - Bags (20 kg):
volume with waste ÷ yield per bag, rounded up
0.756 ÷ 0.00909 = 83.16 bags - Ready-mix:
volume with waste, rounded up to the order step
0.756 → steps of 0.2 m³ = 0.8 m³ - Base:
area × base depth ÷ 1000 × compacted density
7.20 × 50 ÷ 1000 × 2.4 = 0.86 t
How the concrete volume is calculated
The calculator determines the amount of concrete required by first finding the surface area of your shed base. You multiply the length by the width to get the total area in square metres. For a 3 m by 2.4 m shed, the area is 7.2 m². Once you have the area, you multiply it by the slab thickness in millimetres and then divide by 1000 to convert the figure into cubic metres. Using the calculator's starting value of 100 mm for thickness, a 7.2 m² area results in a volume of 0.72 m³.
To ensure you have enough material, the calculator applies a 5% allowance for wastage. This is done by multiplying the volume by 1.05. For the 3 x 2.4 m shed, the volume with waste becomes 0.76 m³. If you choose to use 20 kg bags, the calculator divides this volume by the yield per bag and rounds up to the nearest whole bag. If you choose ready-mix, the calculator rounds the volume up to the nearest 0.2 m³ order step.
Factors that change the concrete amount
Several variables will alter the final quantity of concrete you need to order. The dimensions of the shed and the thickness of the slab both change the volume. While the calculator uses a 100 mm thickness as a starting value, Cement Australia says the minimum thickness for a non-load bearing slab would be 75 mm, and to consult a professional for loads. Increasing the thickness will directly increase the volume of concrete required.
The type of concrete mix also affects the bag count. The calculator uses a specific yield for its calculations, but different brands have different outputs. For example, Cement Australia states that 110 bags of 20 kg are required per cubic metre, while Boral states that 108 bags of 20 kg equate to one cubic metre. You should check the yield on your specific product label to ensure accuracy. Additionally, if you are using a crushed-rock base, the weight of that base depends on the area and the 50 mm compacted depth.
Concrete requirements for different shed sizes
The calculator provides specific results for several shed sizes to help you plan your materials. For a small 3 x 2.4 m shed, you need 84 bags of 20 kg mix or 0.8 m³ of ready-mix. This project also requires 0.86 t of crushed-rock base if a 50 mm compacted base is used.
For a larger 3.6 x 3 m shed, the area increases to 10.8 m². This requires 1.2 m³ of ready-mix concrete or 125 bags of 20 kg mix. The crushed-rock base for this size is 1.3 t. For a large 6 x 3 m shed, the area is 18 m². This requires 2 m³ of ready-mix concrete or 208 bags of 20 kg mix, with a crushed-rock base weight of 2.16 t.
| Shed Dimensions | Area | Volume with Waste | Bags (20 kg) | Ready-mix | Base (50 mm) |
|---|---|---|---|---|---|
| 3 x 2.4 m | 7.2 m² | 0.76 m³ | 84 bags | 0.8 m³ | 0.86 t |
| 3.6 x 3 m | 10.8 m² | 1.13 m³ | 125 bags | 1.2 m³ | 1.3 t |
| 6 x 3 m | 18 m² | 1.89 m³ | 208 bags | 2 m³ | 2.16 t |
Worked example
This section walks through the calculation for a 3 x 2.4 m shed base using the figures from the calculator.
First, calculate the area: 3 m length × 2.4 m width = 7.2 m². Next, calculate the volume: 7.2 m² area × 100 mm thickness ÷ 1000 = 0.72 m³. Then, add the waste: 0.72 m³ volume × 1.05 (5% waste) = 0.756 m³ (shown as 0.76 m³ in the calculator's working). To find the number of bags: 0.756 m³ volume with waste ÷ 0.00909 yield per bag = 83.16 bags, which rounds up to 84 bags. To find the ready-mix: 0.756 m³ volume with waste rounds up to the 0.2 m³ order step, resulting in 0.8 m³. To find the base: 7.2 m² area × 50 mm base depth ÷ 1000 × 2.4 compacted density = 0.86 t.
Common mistakes
One mistake is forgetting to account for wastage. The calculator includes a 5% allowance for wastage, but if you calculate the exact volume without this, you may run short of material. Another error is failing to round the ready-mix volume correctly. The calculator rounds the ready-mix volume up to its 0.2 m³ order step, so round your volume up to the nearest 0.2 m³ rather than using the exact decimal. Check the order step with your supplier.
It is also easy to confuse the weight of the base with the volume of the concrete. The crushed-rock base is measured in tonnes (t), while the concrete is measured in cubic metres (m³) or bags. For a 3 x 2.4 m shed, the base is 0.86 t, which is different from the 0.8 m³ of concrete. Finally, ensure you check the specific yield of your bags, as different brands like Boral and Cement Australia have different bag counts per cubic metre.
Frequently asked questions
What is the minimum thickness for a non-load bearing slab?
Cement Australia says the minimum thickness for a non-load bearing slab would be 75 mm, and to consult a professional for loads. The calculator's starting value is 100 mm.
How much waste should I allow for?
The calculation includes a 5% allowance for wastage.
What is the density of the compacted road base?
The compacted density for road base, DGB, or FCR is 2.4 t/m³.
How many bags of 20 kg mix are in 1 m³?
Boral states 108 bags are required per cubic metre, while Cement Australia states 110 bags are required.
What order step does the calculator use for ready-mix?
The calculator's starting value is 0.2 m³. Check the order step with your supplier.
Sources and assumptions
These are the settings behind every number above. Verified figures link to a source. Editable defaults are common rules of thumb: change them to match your product and your site.
| Setting | Value | Status | Source |
|---|---|---|---|
| concrete bags per m3 20kg cement australia | 110 bags/m3 | Verified 2026-11-18 | Cement Australia Concrete Mix product data sheet (PDS CM rev 3): 110 x 20 kg bags are required per cubic metre. |
| concrete bags per m3 20kg boral | 108 bags/m3 | Verified 2026-11-18 | Boral Concrete Mix product data sheet: 108 x 20 kg bags equate to one cubic metre of mixed concrete. |
| concrete bag yield 25kg | 0.01 m3 | Verified 2026-11-18 | Dricon (Firth) HandiCrete page: 25 kg bag yield 0.010 m3. |
| concrete bag yield 40kg | 0.016 m3 | Verified 2026-11-18 | Dricon (Firth) HandiCrete page: 40 kg bag yield 0.016 m3. |
| concrete slab waste | 5 % | Verified 2026-11-18 | Cement Australia slab calculator page: calculation includes a 5% allowance for wastage and rounds bags up. |
| concrete slab thickness path | 100 mm | Editable default | common practice for paths and patios (Cement Australia how-to uses a 100 mm slab as its example), editable |
| concrete slab min thickness | 75 mm | Verified 2026-11-18 | Cement Australia slab calculator page: minimum thickness for a non-load bearing slab would be 75 mm (consult a professional for loads). |
| concrete readymix order step | 0.2 m3 | Editable default | typical ready-mix ordering granularity, rule of thumb, editable; confirm with local plant |
| concrete readymix consider m3 | 1 m3 | Editable default | Rule of thumb: above about 1 m3 a ready-mix delivery is usually easier than mixing bags. Editable; ask your supplier about minimum orders and short-load fees. |
| concrete base depth | 50 mm | Verified 2026-11-18 | Cement Australia how to lay a concrete slab: excavate an extra 5 cm and compact crusher dust or road base to 5 cm. |
| landscape density roadbase compacted | 2.4 t/m3 | Verified 2026-11-18 | Australian Native Landscapes product weights FAQ: road base/DGB/FCR 2.4 t/m3 (compacted figure). |
| concrete mesh effective length | 5.8 m | Verified 2026-11-18 | InfraBuild ribbed square mesh page: SL72 and SL82 effective area 5.8 x 2.4 m. |
| concrete mesh effective width | 2.4 m | Verified 2026-11-18 | InfraBuild ribbed square mesh page: SL72 and SL82 effective area 5.8 x 2.4 m. |